Our repair progress

May 2017

DSCN2142   DSCN2173

 

 

 

 

 

DSCN2179

Window crowns and memorial stupa are being repainted as a final touch to complete our earthquake repair work

 

April 2017

Office and library block – facade is completed

DSCN2079    DSCN2071

 

 

 

 

 

 

The libraries – newly appointed Librarian, Ven Wangdue Sangpo, has started the huge task of restocking our two libraries with the large number of books which have been in storage since the earthquakes.

The Khenpo Migmar Tibetan Library

DSCN2040   DSCN2045   DSCN2049

The Manjusri Library – Tibetan and other languages

DSCN2061   DSCN2065  DSCN2064

March 2017

Office and library block – office facade upgrade continues

DSCN2015   DSCN2034

DSCN2022

 

Paving – paving around the courtyard and behind the dormitories is being completed

 

 

 

 

 

 

February 2017

Office and library block – a stepped facade had been built below the first floor library and carvings will be added around the windows and columns; the upper walkways are being enclosed with windows, the library and office floors have been laid and supporting columns below the new stepped structure are being strengthened.

DSCN1840   DSCN1854

DSCN1838   DSCN1811

DSCN1834   DSCN1831

DSCN1828

 

 

Painting the whole of IBA – it’s been fascinating to watch these painters nimbly climb flimsy bamboo scaffolding to paint the exterior walls

 

 

 

 

 

Basketball court – our basketball hoops being reinstated

DSCN1843

DSCN1842

January 2017

DSCN1505

 

 

 

Office and library block   Retrofitting of all floors is nearing completion

 

 

 

 

 

DSCN1513

 

 

 

Courtyard   Marble is being laid where the verandas were damaged by the earthquakes

 

 

 

 

 

December 2016

Entrance way  Here are the new inscriptions under the inner archway

dscn0182      dscn0183

Dormitory block The basement and bathroom plumbing have been completed

dscn1062      dscn1067

Office block  The ground floor walls are being bricked up, while the first floor library walls are being demolished to allow retrofitting of the columns

dscn1049

November 2016

Entrance way  The entrance way has been painted and new inscriptions are being added under the inner archway

dscn0040

Office block  Retrofitting and shearwalling of the main admin offices are coming along steadily

dscn0042

Dormitory block  The bathrooms have been tiled, but the plumbing is yet to be done. The floor of the new manager’s office has also been tiled

dscn0055      dscn0056

September 2016

Office block  Columns in the manger’s office are being retrofitted and strengthened, with much of the work being done by hand

img_4886      img_4890

Dormitory block  The external work now needs to be painted, while inside some rooms are looking good, but the bathrooms still need a lot of finishing

img_5059     img_5060     img_5065

                            A new manager’s office on the ground floor of the east dormitory is also shaping up

img_5061

 

August 2016

Office block  Work has started on the office/library block with walls being demolished to expose the columns

walls removed from manager's office

Dormitory block  Major construction on all floors is nearing completion. There is still the plastering, painting and bathrooms to be done

IMG_0593

July 2016

Dormitory block The basement is near completion while work continues on the floors above

IMG_3153        IMG_3156

IMG_3160

June 2016

IMG_3192

IMG_2828Dormitory block  – work has progressed to the second floors of both dormitory buildings

 

 

 

 

 

 

 

 

 

 

 

May 2016

Entrance way lotus petals as well as the central sdom btson dam pa and chu srin are being constructed. See the separate page in this section for an explanation of these.

IMG_0435

April 2016

Dormitory block – retrofitting of columns is almost complete in the basement and is under way on the ground floor. Shearwalling (strengthening the walls with concrete) in the basement is also nearing completion

IMG_2261            IMG_2247

March 2016

IMG_0153

 

Dormitory block –  columns continue to be exposed

 

 

 

 

 

IMG_0090

 

 

Entrance way – the main structure is complete, now elaborating has begun

 

 

 

February 2016

During his brief visit early this month, His Holiness Sakya Trizin inspected our repair progress

IMG_0106 (3) IMG_0088 (2)

 

 

 

 

 

 

 

 

Shrine room – happily we are now able to use the shrine room as per normal for prayers and ceremonies

IMG_0011

Dormitory block – walls are being knocked out of rooms on the first floor of the foreign students’ dormitory to expose the columns for retrofitting

IMG_0025              IMG_0028(2)

IMG_0008

IMG_0003

 

Formwork has been put up around the bolstered columns for further strengthening as shear walling, while excavation to expose more columns continues.

IMG_0013

 

 

Shear walling  has begun with concrete being poured into the formwork.

 

 

 

January 2016

Dormitory block – metal work (re-bar) for the foundational concrete slab is being laid

Excavations to expose the in the basement columns have proceeded and retrofitting has begun with steel supports and ties put in place

IMG_1135

IMG_1181

 

IMG_1141IMG_1185

 

 

Entrance way – is continuing to take shape

IMG_1179

December 2015

IMG_1090

 

Dormitory block – The main repair work has started – retrofitting the dormitory and office/library blocks. This means the walls and floors have to be cut away from the supporting columns, which are then rebuilt in a much stronger, earthquake-resistant fashion. Beginning in the basement, the work will gradually move up to the fourth floor. It could take more than a year till completion – we have to wait and see!

 

IMG_0880

 

Entrance way – Work has restarted on the entrance way. The design for our new entrance was created by one of our more artistic monks.

 

 

 

 

IMG_0882

 

Shrine room entrance – The passageway outside our shrine room, at the top of the stairs, lost its ceiling during the earthquakes. This has now been repaired.

 

 

 

November 2015

IMG_0865

 

Main shrine room – We have repaired the ceiling and floor of our main shrine room. The April 2015 earthquakes had caused the original ceiling to collapse, damaging the floor. Both have now been restored.

 

 

 

IMG_0871

 

Perimeter wall – Our perimeter brick wall was left leaning dangerously out over the surrounding street, so it was vital to repair it quickly. This has been achieved.

 

 

 

IMG_0874

 

Entrance way – Our entrance archway collapsed and the gates were damaged. Reconstruction has begun on these, but has been halted due to problems caused by the current disruption to the flow of materials from India into Nepal.